CAPACITY PLANNING IN AGILE SCRUM

 

1.      What is Capacity Planning?

2.      Benefits of Capacity Planning

3.      How to do the Capacity Planning

4.      Examples of Capacity Planning

5.      Excel Template Sample

What is Capacity Planning?

CAPACITY PLANNING is the Available bandwidth or Productive hours of the Team members to deliver the product.

PRODUCTIVE HOURS: The number of hours that the team members could spend to do the Actual work in the project

Actual Hours: The Actual hours will be calculated after deducting the hours planned for the sprint events / ceremonies

For Example:

If the team members work 8 hours per day

around 6 hours will be considered as Productive hours

Remaining 2 hours will be used for sprint events , internal discussions

Availability will be measured in Hours

CAPACITY PLANNING will be done for the Team members for the Entire Sprint

BENEFITS OF CAPACITY PLANNING – Why should we do the capacity planning


1. Understand the Available Bandwidth  for the team to commit and complete the User stories.

 2.Help the Team members to do the Better Planning 

Capacity planning will help the team members to do the better planning and task allocation of sprint goal .

 3. Better visibility of the Team members Availability  

Capacity Planning gives the better visibility about Team members Availability to the Product owner(PO) 

4. Avoid Task Overload and Frustration  : Capacity Planning will help to Avoid Task Overload / Frustration 

5. Plan the Sprint Goal Effectively : Capacity Planning will help to plan the sprint goal effectively and provide the Realistic  commitment for the sprint . 



How to do the Capacity Planning ?

There are 6 key points to do the Capacity Planning

Techniques of Capacity Planning

Example:

 

Basic Equation:

1.      No.of Team Members x No.of Days in the Sprint x No.of Productive Hours 

2.      Sprint Duaration = 3 Weeks for the Team

                             = Week1 | Week 2 | Week3

                             = 15 Working Days => for the # 3 Week Sprint

                                                                   (By Excluding Saturday and Sunday’s )

                                                     (Working Days are considered from Monday to Friday Only)

3.      Standard Working duration = 8 Hours / Day                       

4.      Total No.of  Vocation days planned by the team = 4 Days

5.      No.of Working Hours considered for the Vacation days = Zero Hours

       ( 0 – Hours )

6.      First “Thursday” is Holiday for All the Team Members

(Work Hours for that day is Zero)

Explanation:

1.      Out of 8 hours per day è 6 hrs are considered as Actual Work => 2 hrs are planned for Meetings , Discussions etc

2.      So we can see : 6 hrs per day for Each team members

3.      On the First day of the sprint ,

Team will spend 4hrs -à 1 week for “Sprint Planning Meeting”

So the Capacity is considered as 4hr for each Person à on the First Day of the sprint

4.      Capacity of Each team member work is shown in the last column at the right side

From the Example :

For Joe , its 82 hrs

For Kumar, its 70 hrs etc

This is the individual Team member capacity for this 3 week sprint .

 

Total Capacity of the Team members is calculated – by Adding all the Team members capacity

As per Example

  Total Capacity of the Team = 552 hours

                           So 




 

 

 

 

 

 

 

 

 

 

 

 



                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                  

Comments

Popular posts from this blog

What Does a SM-SCRUM MASTER do “All the Day”

When to choose scrum and when to choose kanban? Explained with examples

Kanban board setup for AMS teams in SAP