To determine how many sprints it will take to complete 59 user stories and how many story points to assign to each user story, we need to break this down step-by-step: Step 1: Estimate the Story Points Assess the Complexity : First, you need to estimate the complexity of each user story. Story points are often assigned based on factors like effort, risk, and complexity. Use techniques like planning poker or t-shirt sizing to estimate. Typical Scale : Story points are often estimated using Fibonacci-like sequences (e.g., 1, 2, 3, 5, 8, 13, 21) or other scales that represent effort. Step 2: Determine Team Velocity Velocity : Velocity is the number of story points a team can complete in one sprint. For example, if the team completes 30 story points in a 2-week sprint, their velocity is 30. Historical Data : If the team has historical data, use that to determine their average velocity. If not, start with a rough estimate based on team capacity. Step 3: Calculate Number of Sprints Once...