To calculate how many user stories can be assigned in a 2-week sprint
To calculate how many user stories can be assigned in a 2-week sprint with 3 developers and 1 QA, where each developer works 6 hours per day, we need to consider the total available hours and how many story points the team can realistically complete.
Example Calculation
Assumptions:
- Sprint Duration: 2 weeks (10 working days).
- Work Hours per Day per Developer: 6 hours.
- Total Developer Hours: 3 developers × 6 hours/day × 10 days = 180 hours.
- Work Hours per Day for QA: 6 hours.
- Total QA Hours: 6 hours/day × 10 days = 60 hours.
- Average Velocity: Assume the team typically completes 25 story points per sprint.
Estimating User Stories
Allocate Story Points to Developers:
- Let’s assume each story is 5 story points. If each story requires approximately 30 developer hours (5 story points/story), the developers could handle 6 stories:
QA Capacity:
- If each story requires about 10 QA hours for testing, the QA can handle 6 stories in 60 hours.
Since both the developers and QA can handle 6 stories, you can assign 6 user stories to the sprint, totaling 30 story points.
Final Notes:
- This assumes all stories are of equal size (5 story points) and the estimates are accurate.
- Adjust based on any known variability in story sizes or unexpected tasks.
This estimation balances developer and QA workload, allowing smooth progress through the sprint.
Comments
Post a Comment