how many story points we can allocate for a sprint and how
To determine how many story points you can allocate for a sprint, you need to consider the available hours, the number of developers, and the relationship between hours and story points. Here’s how you can calculate it: Step 1: Determine Total Available Hours for the Sprint Given: Total hours for the sprint : 180 hours Number of developers : 3 Step 2: Estimate Story Points Per Developer Assume that one story point represents a certain number of hours of work. For example: 1 story point = 8 hours Each developer has 60 hours available: Hours per developer = 180 hours 3 developers = 60 hours/developer \text{Hours per developer} = \frac{180 \text{ hours}}{3 \text{ developers}} = 60 \text{ hours/developer} Hours per developer = 3 developers 180 hours = 60 hours/developer Given this, the number of story points each developer can handle: Story points per developer = 60 hours 8 hours/story point = 7....